When Do Chinese Factories Close for Chinese New Year? A Glass Bottle Ordering Guide

Quick Answer: Chinese factories usually start slowing down about 20 days before the Chinese New Year holiday, trucking and freight bookings stop about 15 days before, and normal operations return at least one week after the holiday ends. For stock glass bottles with your logo, order about 10 weeks before the holiday starts.

  • The official Chinese New Year holiday is usually around 9 days, but the real disruption lasts 5 to 6 weeks.
  • Printing, caps and packaging slow first, about 20 days before the holiday; logistics stops about 15 days before.
  • Production and shipping recover at least one week after the official holiday ends.
  • Glass furnaces run 24 hours a day, 365 days a year, so the slowdown comes from people and logistics, not furnaces.
  • In 2027 the holiday runs from 5 to 13 February, so stock orders with a printed logo should be placed by the end of November 2026.

Why do so many spring orders from China arrive late, even when the holiday is only nine days long? Because the official holiday is only the centre of a much longer slowdown. Chinese New Year moves every year, between late January and mid February, but the pattern around it stays the same. This guide explains that pattern, gives you simple rules to calculate your own order deadline in any year, and uses 2027 as a worked example.

Cartons of glass bottles stacked on wrapped pallets in a warehouse before the Chinese New Year holiday

How long do Chinese factories really close for Chinese New Year?

Chinese factories are affected for about 5 to 6 weeks around Chinese New Year, even though the official public holiday is usually around 9 days. The holiday follows the lunar calendar, so it falls on a different date each year, and China’s State Council announces the exact holiday dates each November for the following year. For 2027, the holiday runs from 5 to 13 February, with 31 January and 14 February as working days[1].

Most factory workers travel back to their home provinces for the festival, often far from the factory. They leave before the holiday and many return after it, so output falls well before the official start date and takes time to recover afterwards.

What is the typical Chinese New Year slowdown pattern?

From our experience, the slowdown follows the same pattern every year. You can apply it to any year once you know when the official holiday starts and ends.

StageWhen it happensWhat it means for your order
Slowdown beginsAbout 20 days before the holidayScreen printing, cap and packaging suppliers start to stop; new orders queue for after the holiday
Logistics stopsAbout 15 days before the holidayTrucking and freight bookings wind down; goods not yet collected wait until after the holiday
Official holidayUsually around 9 daysOffices and most production closed
RecoveryAt least 1 week after the holiday endsWorkers return, printing, packaging and logistics restart gradually

Glass production itself does not stop. Our glass furnaces run 24 hours a day, 365 days a year, and are never switched off for the holiday. What stops is everything around them: screen printing, caps, cartons, inspection, packing and trucking, which all depend on workers and outside suppliers.

Timeline of the Chinese New Year factory slowdown and recovery

How do you calculate your order deadline before Chinese New Year?

Work backward from the start of the official holiday. Your goods need to be printed, packed and collected before logistics stops, about 15 days before the holiday, and printing has to finish before decoration suppliers stop, about 20 days before.

For stock glass bottles with your logo, our lead times are 7 to 15 days for the logo sample and 15 to 25 days for production, with a minimum order of 2,000 pieces. Add a few days for artwork confirmation and sample approval, and the total can reach about 7 weeks. Adding that to the 20-day slowdown gives a simple rule:

  • Stock bottles with a printed logo: order about 10 weeks before the holiday starts.
  • Plain stock bottles: a little later is possible, but freight space before the holiday is the limit, so confirm lead time and shipping with your supplier early.
  • Custom mold projects: 35 to 45 days for the mold and sample plus 35 to 45 days for production. A mold started in the autumn can have its sample approved before the holiday, with production after the recovery.
  • Freight: book at least three weeks before your cargo is ready, as logistics providers recommend for the pre-holiday rush[2].

What does the 2027 timeline look like?

Chinese New Year 2027 falls on Saturday 6 February, and the official holiday runs from Friday 5 February to Saturday 13 February[1]. Applying the pattern above gives this timeline for glass bottle orders.

Milestone2027 date
Last date to order stock bottles with your logoEnd of November 2026
Logo sample approvedMid December 2026
Printing and packaging finishedBefore mid January 2027
Slowdown beginsMid January 2027
Trucking and freight bookings stopLate January 2027
Official holiday5 to 13 February 2027
Gradual recoveryFrom around 20 February 2027

A custom mold started in late November or December 2026 can have its sample approved before the holiday, with production starting once operations recover after 20 February, which puts delivery at around April 2027.

When is Chinese New Year in 2028, 2029 and 2030?

Chinese New Year falls on 26 January 2028, 13 February 2029 and 3 February 2030. The official holiday dates for these years have not been announced yet, so the table below is an estimate, assuming the holiday starts around New Year’s Eve and lasts about 9 days. Check the official dates each November and adjust.

YearChinese New YearOrder stock bottles with logo by (estimate)Slowdown begins (estimate)Recovery (estimate)
20276 FebruaryEnd of November 2026Mid JanuaryFrom around 20 February
202826 JanuaryMid November 2027Early JanuaryAround 9 February
202913 FebruaryEarly December 2028Late JanuaryAround 27 February
20303 FebruaryLate November 2029Mid JanuaryAround 17 February

Note how much the dates move. In 2028 the holiday starts in late January, so the order deadline falls in mid November, and printing suppliers may begin to slow down shortly after the New Year holiday on 1 January.

Can you still send enquiries and approve samples during the holiday?

You can still send enquiries during the holiday, but replies and production will be slower. Sales teams often check messages during the break, while sampling, printing and production wait until operations recover. Any order confirmed during the holiday joins the queue of orders waiting for the restart.

Samples are the step most often forgotten. If you need a physical sample before a spring order, ask for it at least two months before the holiday, so it can be checked and approved before the slowdown. Send final logo files, colour references and print positions early too, so printing can start straight away.

How can you protect your stock over the holiday every year?

The safest approach is to plan the holiday into your annual purchasing calendar, rather than reacting each winter. Experienced buyers usually combine three steps.

  1. Order extra cover before the break. Calculate how many bottles you use over the 5 to 6 weeks of disruption plus your shipping time, and add that to your last pre-holiday order. Glass bottles do not expire, so holding extra stock carries little risk beyond warehouse space.
  2. Book the first post-holiday slot. Place your next order before the holiday, so it is first in line when production recovers.
  3. Ask your supplier for four dates in writing. Last date to confirm orders, last production date, last dispatch date and the date normal production resumes.

Packing matters more than usual when goods wait in warehouses or ports over the holiday. Our article on preventing glass jar breakage during shipping covers carton, divider and pallet choices that hold up through longer storage. For what drives custom bottle costs and minimum orders, see our custom bottle pricing and MOQ guide.

Chinese New Year dates and estimated glass bottle order deadlines for 2027 to 2030

Which glass bottles are easiest to order before the holiday?

Stock bottles are the easiest to order before the holiday because no mold is needed. Stock ranges such as beverage and soda bottles, honey jars and pickle jars can be printed, frosted or colour sprayed with your branding from 2,000 pieces, and small perfume bottles from 3,000 pieces. Choosing a stock bottle for your pre-holiday order, then moving to a custom mold after the holiday, is a common way to keep supply steady.

Conclusion

Chinese New Year moves every year, but the slowdown around it follows a reliable pattern: about 20 days of slowdown before the holiday, logistics stopping about 15 days before, and recovery at least a week after it ends. Use that pattern to set your order deadline each year, about 10 weeks before the holiday for stock bottles with your logo. For 2027, that means ordering by the end of November 2026. To check what can still ship before the holiday, send us your bottle type, quantity and target arrival date through our contact page.

FAQ

How long do Chinese factories close for Chinese New Year?

The official holiday is usually around 9 days, but the disruption lasts about 5 to 6 weeks. Factories start slowing about 20 days before the holiday, and normal operations return at least one week after it ends.

When should I order glass bottles before Chinese New Year?

For stock bottles with a printed logo, order about 10 weeks before the official holiday starts. For Chinese New Year 2027, that means ordering by the end of November 2026.

When is Chinese New Year in 2027, 2028, 2029 and 2030?

Chinese New Year falls on 6 February 2027, 26 January 2028, 13 February 2029 and 3 February 2030. The official 2027 holiday runs from 5 to 13 February.

When does shipping stop before Chinese New Year?

Trucking and freight bookings usually wind down about 15 days before the official holiday. In 2027, that is late January.

Do glass furnaces stop during Chinese New Year?

No. Glass furnaces run 24 hours a day, 365 days a year. The slowdown comes from screen printing, caps, packaging, inspection and logistics, which depend on workers and outside suppliers.

Can I order a custom glass bottle mold before Chinese New Year?

Yes. A mold started in the autumn can have its sample approved before the holiday, with production after operations recover. For 2027, a mold started in late 2026 means delivery around April 2027.


References:
[1] General Office of the State Council of China, via Xinhua. “Notice on the arrangement of some holidays in 2027.” 5 November 2026. https://www.news.cn/politics/20261105/f90cd6ad4df94ab4833b141e52ccfc13/c.html
[2] SEKO Logistics. “Chinese New Year 2027: Shipping and Factory Closure Deadlines for UK Importers.” https://www.sekologistics.com/en/resource-hub/knowledge-hub/china-to-uk-shipping-lunar-new-year-2027/

Serena Chen

Project Manager

Hey,I’m the author of this post, with extensive experience exporting to 36 countries and managing 82 international packaging projects. Specializing in premium OEM/ODM glass bottle solutions to help beverage, spirits, food, cosmetics, and pharmaceutical brands create distinctive and sustainable packaging.